Wyong Hospital Redevelopment Prototype

Delivering functional, modern hospitals, which are ready to provide critical care from day 1 is essential. Facilities which meet the current and future needs of the local community, achieve the best long-term outcomes for patients and frontline staff. By partnering with clinical and hospital staff and representatives from the Local Health District and Health Infrastructure we are able to design and build state of the art hospital facilities which support the delivery of vital health care in our community.

On the Wyong Hospital Redevelopment, this approach led to the construction of a several prototype on site, which is offering users the chance to see and test some of the future critical clinical spaces and provide valuable input into the design finalisation process.

Our Senior Site Manager on the project, Dane Lalic, says it’s about much more than a ‘Measure Twice, Cut Once’ approach;

Building a high-quality prototype with the necessary specifications, finishes and equipment allows the end user to live and breathe the design and ensure the completed facility will offer them a fully functional space to provide patients with the best possible care. As a Central Coast local and having delivered a number of hospitals in my career, I understand how important Wyong Hospital is for the community and the positive outcomes which can be achieved through early engagement and collaboration.

It’s important for us to understand the end user of any building; the more we know about their operational rhythms and what is important to them, the better we can deliver a facility which meets their needs. This approach is of course all the more critical when you are delivering social infrastructure projects which provide such important services for the community; it’s a huge source of pride for all of us at RCC to be able to play a role in building state of the art health facilities

 

Dane Lalic – RCC Senior Site Manager

 

Works have progressed significantly since the first sod was turned on site in late 2019. The construction and fit out of the prototype occurred in conjunction with the early stages of the hospital main development to ensure ample time for end users and representatives from the Central Coast Local Health District (CCLHD) and Health Infrastructure NSW to take advantage of the mock facilities. The project team erected a shed on site and delivered the build and integrated fit out to the specifications and finishes required. Providing the most practical and immersive user experience possible is crucial to ensuring that the completed Wyong Hospital campus supports the operational rhythms of hospital staff and patients and facilitates the provision of critical health care services to the growing Central Coast community population. The sample building is now far from its humble beginnings as a shed and, although only a fraction of the size of the future hospital, now contains inpatient and emergency department rooms all delivered to the scale. The RCC project team worked closely with hospital staff and end users, the CCLHD, Health Infrastructure NSW, Colliers Project Leaders, project consultants and subcontractors to carefully plan and deliver the high-quality prototype, complete with equipment, ahead of the user inspections and testing earlier in the year.

Staff will continue to visit the prototype shed, working with the team to select furnishing, fittings and equipment. It will also be used in the future for training and education sessions as staff prepare to move into the new building.

 

 

 

 

 

 

 

 

Hear from the Central Coast Local Health District team about the impact this prototype facility will have on the final hospital and their end user experience.

 

MORE ABOUT THE WYONG HOSPITAL REDEVELOPMENT

The Wyong Hospital project involves the delivery of a new Clinical Services Building, which will provide the local Central Coast community with a new Emergency Department, additional operating theatres, and ICU/HDU capacity, mental health expansion, additional inpatient beds for medical and acute services, clinical and non-clinical support services and parking.

Due for completion in 2022.

Take a virtual tour through the proposed new facilities, with this short Wyong Hospital Redevelopment fly-through:

 

 

Molecular Horizons – University of Wollongong

Molecular Horizons is a purpose-built facility dedicated to illuminating how life works at a molecular level and solving some of the world’s biggest health challenges.

The opportunity to be involved in delivering this high impact research facility is as rewarding as our collaborative delivery experience, partnering with University of Wollongong and our team of consultants and subcontractors.

 

DELIVERING MOLECULAR HORIZONS

Delivering buildings we are proud of, and knowing the important contribution they make to our community is why we love what we do.

Hear from those who were part of the Molecular Horizons project about their experience of working with RCC to deliver this incredible building.

 

“The researchers that are in the building they love it. Here they are in a state-of-the-art bright building with new facilities, expanded space and a lot more research capability for them as well and also a higher level of lab certification so they can do higher levels of research.”

Blake Preston
Senior Manager Project Delivery – University of Wollongong

 

“this was a project where the end users requirements, the scientists, and the process of construction and building was so tightly integrated I think this was a real example of a team of people, academics and construction people, who really had to find each other early on and become a real team with tight and frequent communication. And that was a process that was really good to see that happen very efficiently.

I have received lots of advice in my career never to be involved with the construction of a new building, but I have to say having done it now it was just an absolute pleasure and a real adventure and I think that’s in large part because of RCC”

Antoine Van Oijen
Director, Molecular Horizons
School of Chemistry and Molecular Bioscience – University of Wollongong

 

 

MORE ABOUT THE MOLECULAR HORIZONS PROJECT

Design, construction and integrated fit out of the five-storey facility within the operational University of Wollongong campus. The building includes office and administration areas with meeting and conference rooms; research and chemistry laboratories (including PC2 and BC2 certified); animal housing; and an astronomy and chemistry roof platform with rooftop mechanical plant.

These state-of-the-art facilities house some of the world’s most revolutionary technology, including Australia’s most powerful biological electron microscope, the Titan Krios cryo-EM microscope.

Hear more about University of Wollongong’s vision behind this world-leading Molecular Life Sciences facility.

 

 

MORE ABOUT MOLECULAR HORIZONS RESEARCH

Research Grant for Director OF Molecular Horizons

Congratulations to UoW researcher, Distinguished Professor Antoine van Oijen who was recently awarded $1M for antimicrobial resistance research – a project which will develop a new approach to understanding and tackling drug resistance.

Read more

 

First Publication from Molecular Horizons

“The first publication out of the facility was something called ATP synthase; that’s a protein in your body that creates the energy source for life which is what your cells use; which is Adenosine triphosphate (ATP) so that was exciting”

James Bouwer
General Manager of Cryo Electron Microscopy – Molecular Horizons
School of Chemistry and Molecular Bioscience – University of Wollongong

 

 

Stage 1B of Inverell Hospital

The RCC Hunter New England team is incredibly proud to have been awarded the next stage of the Inverell Hospital Redevelopment.

In uncertain times where there is much reflection on the importance of our health care facilities and workers, we are celebrating the role we are able to play in delivering quality facilities for our hospital staff to keep our communities healthy and well. For the members of the RCC team, whose family and friends rely on this local hospital, there is a shared sense of pride in the contribution their work will make to their community, now and for future generations.

For RCC, working on critical projects which support the delivery of essential services in our local communities is an important part of what we do. We take pride in our work and the impact it has, particularly in regional and remote areas. As they approach the completion of the first stage of the Inverell Hospital upgrade, the team say their involvement in this project means so much to them and their families, beyond the opportunity to be employed to do what they love each day.

 

THE INVERELL HOSPITAL PROJECT

Stage 1a (RCC Completed 2019)

The project involves the alteration and refurbishment of the Inverell Hospital, essentially doubling the existing space and improving flexibility for staff. Facilities include:

  • Emergency Department including emergency care for children and mental health-related presentations
  • Inpatient Unit, with paediatric, maternity and birthing facilities and general adult services including palliative care
  • Medical Imaging space including identified future expansion zone
  • Operating Theatres
  • Central Sterilising Unit
  • Day Surgery Unit (increasing from 1 space up to 6)
  • Renal Dialysis unit
  • Refurbishment of main entry & admissions area
  • Mortuary
This Stage (1B)

This stage specifically entails the decanting of staff and patients from the existing hospital floorspace into the newly completed Stage 1a building, as well as the demolition, refurbishment and upgrade of the existing Inverell Hospital building into a Community Health Centre. This facility will provide additional community services for chronic disease, allied health, oral health and women and paediatric services, as well as office and education spaces.
This stage will also include new external carparking, services upgrades and CT scanner fit out.

 

THE PASSIONATE TEAM DELIVERING INVERELL HOSPITAL

Beyond the physical building, the completed Inverell Hospital facility will have a long-lasting legacy for the local Inverell community and those in the surrounding areas. We asked a few of our team to share what the project means to them:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6 MBA Awards for Excellence in Construction

RCC is proud to announce we took home 6 awards at this year’s Master Builder Association Excellence in Construction Awards

  • The Epicentre, Baulkham Hills – Tertiary Buildings $30m – $50m
  • Bellevue Hill Public School – Public Schools Open Price Category
  • Airtrunk Sydney Data Centre – Phase 1, Huntingwood – Communications Buildings Open Price Category
  • Northside Clinic, St Leonards – Health Buildings $20m – $60m
  • Leichhardt Green – Residential & Mixed-Use Development Buildings up to $200m
  • NSW Best Use of Concrete – on the Bellevue Hill Public School project

For us, success is about completing a project that RCC, our clients, subcontractors and consultants can all be proud of. Congratulations to everyone who played a part in the design and delivery of these award-winning projects.

 

We believe our ability to win this number of awards, across several social infrastructure sectors is the result of our consistent commitment to a collaborative approach. Our teams partner with clients, consultants and suppliers to design and deliver quality facilities with the end user in mind; we’re proud to be delivering residences, workplaces, community, education and health facilities for our local communities.

 

Want to know more about our 2018 award winning projects?

The Epicentre, Baulkham Hills

Client:   Hills Christian Centre Limited
Award:  Tertiary Buildings $30m – $50m

Bellevue Hill Public School

Client:   NSW Department of Education
Award:  Public Schools Open Price Category &
Best Use of Concrete

Airtrunk Sydney Data Centre – Phase 1, Huntingwood

Client:   Sydney Air Trunk Land Trust
Award:  Communications Buildings Open Price Category

Northside Clinic, St Leonards

Client:   Ramsay Health care
Award:  Health Buildings $20m – $60m

Leichhardt Green

Client:   Greenland Holding Group
Award:  Residential & Mixed-Use Development Buildings   up to $200m

 

 

 

Delivering Health Facilities to Support Regional NSW

In addition to supporting the growth of world class health care in Sydney, RCC is committed to delivering support services in regional and rural NSW.

While our head office is in Sydney, we provide localised client service with offices in Tamworth, Newcastle and Canberra. Delivering projects in regional locations is a large part of our business. On average, 30% of our projects have been delivered regionally, including major projects such as the Tamworth Hospital.

NSW Health has adapted the traditional hospital structure to reflect the changing rural and remote environments that they service.

“The NSW Rural Health Plan: Towards 2021 aims to strengthen the capacity of rural health services to provide world class connected and seamless care for people living in regional, rural and remote NSW.”

In response, RCC is leveraging our regional expertise to support NSW Health’s vision for improved infrastructure in regional and rural NSW.

Maintaining a regional presence allows us give back in local communities, whilst driving local industry participation and regional growth.

We look forward to a continued partnership with NSW Health and the local communities in which we operate.

 

 

 

 

 

 

 

 

 

Lawson Clinic Sod Turning Ceremony

Lawson Clinic Sod Turning

The first soil has been turned on the Lawson Clinic project!

The ceremony for the mental health facility in the NSW suburb of Gordon, was attended by both Lawson Clinic and RCC personnel as well as local politicians, Paul Fletcher (member for Bradfield) and Alister Henskens (member for Ku-Ring- Gai).

Continue reading “Lawson Clinic Sod Turning”

St Leonards Clinic Topping Out 1

St Leonards Clinic Topping Out

Topping out celebrations for the St Leonards Clinic project were carried out on site with a lunch as the traditional tree was lifted onto the completed structure. Ramsay Health Care and Northside clinic staff as well as several doctors and nurses who will use the facility attended, and it was our pleasure to provide them with a site tour and take them through the prototypes for the future clinic bedroom with ensuite and doctors consult room.