Client: Health Infrastructure
Architect: Conrad Gargett
Delivery Form: Design & Construction
Location: Inverell, NSW
Value: $9m
Completion date:  April 2021

Stage 1B specifically entails the decanting of existing staff & patients from existing hospital floorspace into completed stage 1A new building, demolition, refurbishment & upgrade of the existing Inverell Hospital from existing facilities. The building will become a Community Health Centre, specifically to provide additional facilities to the Inverell & wider Gwydir community for:

  • Chronic Disease
  • Allied Health
  • Oral Health
  • Women’s & Children’s Health
  • Paediatric Services
  • Office and Education

The stage also includes:

  • A new external carparking
  • External Services upgrades
  • Recently approved CT scanner warm shell fit-out scope
  • Possible additional Re-Roofing upgrade pending works approval