Smalls Road Public School

Design & Construction of a new 3 storey circular public school at the former Ryde High School site for up to 1000 students and 70 staff.

The new public school will consist of:

  • 43 learning spaces including multi-function rooms & 3 for special education purposes;
  • Two-level library, school hall, out-of-hours care facilities (OOSH), teaching & administrative staff offices, and canteen;
  • Indoor & outdoor recreational facilities & COLA;
  • Extended road widening works on Smalls Rd to accommodate additional kiss & drop facilities (16 spaces) & limited time parking (10 spaces);
  • Refurbishment of existing & construction of new car parking facilities for 47 spaces;
  • Associated landscaping including refurbishment of multipurpose sports courts & fencing.

Client: NSW Department of Education
Architect: Conrad Gargett
Delivery Form: Design & Construction
Location: Ryde, NSW
Value: $38m
Completion date: January 2020

Wentworth Point Public School

Construction of a new primary school to accommodate up to 600 students. Within the 3 buildings (2x single level & 1x 3 level), the school consists of 14 teaching spaces, 4 special education classrooms, multipurpose hall with theatre equipment, administration buildings, library areas & COLAs for engaging and interactive learning and vast landscaped areas for recreational use.

Client: NSW Department of Education
Architect: Group GSA
Delivery Form: Design and Construction
Location: Wentworth Point, NSW
Value: $16.6m
Completion date: December 2017

TRN House

Oran Park Commercial 1

The project involves the design and construction of a new 6 storey, 30,000m2 distribution centre that incorporates the following key features:

  • 3 Storey Basement Carpark with a total of 320 vehicle spaces and 20 motorcycle spaces
  • 3 Passenger Lifts servicing 9 Levels & 1 Car Lift servicing the roof
  • Landscaped roof-top terrace
  • Associated street level landscaping works; and
  • Dedicated loading / delivery dock area

Client: Greenfields Development Company
Architect: Allen Jack & Cottier
Delivery Form: Design and Construction
Location: Oran Park, NSW
Value: $45m
Completion date: April 2020

Airtrunk Data Centre – Huntingwood

Design and construction of phase one included the delivery of a 12,000sqm data centre facility comprising of a two level data centre which was broken into 8 data halls boosting 20mw of capacity cooled by 20 CRAC (Computer Room Air Conditioning) units per hall (100 in total). The tech building spanning 4,800m2 over 3 stories located adjacent to the main data hall will facilitate all the amenities and tenant areas for current and future use including meeting and communications rooms, and 3 lifts.

Client: Airtrunk
Architect: DEM Australia
Delivery Form: Design and Construct
Location: Huntingtonwood, NSW
Value: $87.8m
Completion date: September 2017

Bellevue Hill Public School

A two stage construction comprising of a new 4 level reinforced concrete and precast building with educational spaces and library. Stage 2 includes a new Covered Outdoor Learning Area (COLA), Canteen facilities, extensive landscaping and external works.

Client: NSW Department of Education
Architect: Group GSA
Delivery Form: Construction Only
Location: Bellevue Hill, NSW
Value: $14.9m
Completion date: August 2017

Hornsby Ku-ring-gai Hospital Carpark

The project consisted of decanting and demolition of existing Buildings 10 (Physiotherapy) and Building 1 (Cardiology), service diversions and enabling works for commencement of the new multi-storey car park.

The carpark works involved a new 6 level (13 split level) reinforced concrete multi-storey staff and public carpark to accommodate 512 cars. In conjunction with the carpark works, room conservation and additional amenities were constructed within the existing STAR building.

RCC were also directed to complete the Stage 2 Early Works which consisted of:

  •  Installation of a communication cabling ring main & medical gas ring main.
  •  Refurbishment of Building 54
  •  Demolition of Buildings 15, 21, 34 & 47
  •  Demolition of cottages 95 & 97
  •  Construction of a modular building (57) and refurbishment of Building 1

Client: Health Infrastructure NSW
Architect: Nettleton Tribe
Delivery Form: Design & Construct
Location: Hornsby, NSW
Value: $30m
Completion date:  December 2018

The University of Sydney – F07 LEES

The LEES 1 Building will consolidate the School of Molecular Biology and School of Biological Sciences within the Faculty of Science. An 8 level, USYD Sustainability Framework ‘Silver’ rated educational facility that consists of teaching support areas, hazardous materials handling areas, laboratory spaces for undergraduates and post graduates, and a public domain research area. The project is the first phase of a broader Life and Physical Sciences consolidation and a landmark project for the University of Sydney.

Client: University of Sydney
Architect: HDR Rice Daubney
Delivery Form: DD&C
Location: Sydney, NSW
Value: $64m
Completion date: September 2018

The Miller

The project generally comprises the demolition of the existing office building, which consists of a ground floor, levels 1 –L13, mezzanine floor to L14, rooftop plant room, and two storeys of basement car park. Construction of a new mixed use apartment building comprising 6 basement levels, 1 ground retail level containing 1 tenancy, and the construction of a 23 storey structure (plus plant room level, roof and 5 levels of basement), which will be a mixed use development of residential units, a retail units and serviced apartment units as follows;

  •  183 Residential Apartments.
  •  100 Serviced Apartments (Quest Hotel)

Client: Yuhu Group
Architect: PTW Architects
Delivery Form: Design & Construct
Location: North Sydney, NSW
Value: $108.6 m
Completion date: February 2019

Regiment Student Accommodation

RCC has been engaged by the University of Sydney to redevelop the H01 Regiment Building, H02 Darlington Centre. The project involves the demolition of the current building and the construction of a new mixed use development integrating affordable student accommodation, community facilities and teaching spaces.

The new mixed use redevelopment will consist of:

  • 656 single dorm size rooms of Circa 10.1-10.3m2 min. 5% (33 rooms) shall be Accessible/Adaptable rooms Circa 13.8m2.
  • Two 2-bedroom apartments for the Deputy and Head of Hall Accommodation
  • Communal lounges, games, study and music rooms, flexi spaces and kitchen facilities.
  • Shared toilet and bathroom amenities.
  • Shared communal laundry facilities
  • Bike Storage for 175 bikes and staff end of trip facilities.
  • Teaching hub, technology hub, theatre and teaching Rooms.
  • Office space and meeting rooms for Student Accommodation support staff.

Public landscaped forecourt, private courtyards and landscaped roof terraces

Client: University of Sydney
Architect: NettletonTribe
Delivery Form: Design & Construct
Location: Darlington, NSW
Value: $73 m
Completion date: February 2019

Superlot 11 – Illume

Design and construction of 3, 5 storey multi – unit residential buildings comprising 179 dwellings, shared basement parking for 226 vehicles and associated landscaping works, including a through site public pedestrian link.

Client: TA Little Bay Pty Ltd
Architect: Tony Caro Architecture
Delivery Form: Design & Construct
Location: Little Bay Cove, NSW
Value: $76.3m
Completion date: June 2018